Albemarle Logo
File #: 23-199    Version: 1 Name:
Type: Work Session - Information Status: Work Session
File created: 2/22/2023 In control: Board of Supervisors
On agenda: 4/5/2023 Final action:
Title: VDOT/Albemarle County FY 24-29 Secondary Six-Year Plan
Attachments: 1. Att.A - Secondary Six-Year Plan Report April 2023, 2. Att.A1 - Draft Albemarle County SSYP FY2024-2029, 3. Att.A2 - Albemarle County Unpaved Road Policies and Review Process, 4. Att.A3 - FY24 Albemarle County Priority List for Secondary Road Improvements, Unpaved Roads, 5. Att.A4 - FY23-28 Approved SSYP
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA DATE: 4/5/2023

TITLE:
Title
VDOT/Albemarle County FY 24-29 Secondary Six-Year Plan
BODY

SUBJECT/PROPOSAL/REQUEST: Review the FY 2024-2029 Secondary Six-Year Plan priorities and recommendations

ITEM TYPE: Regular Action Item

STAFF CONTACT(S): Richardson, Walker, Rosenberg, Herrick, Filardo, McDermott, Karina-Plun

PRESENTER (S): Alberic Karina-Plun

LEGAL REVIEW: Yes

REVIEWED BY: Jeffrey B. Richardson

BACKGROUND: This agenda item is intended to present information on the Albemarle County Secondary Six-Year Plan (SSYP) and road paving priorities in advance of the development and approval of the FY 2024-2029 SSYP in May 2023.

The SSYP allocates funding for construction, maintenance, and improvement of roads in the state secondary system. The funds allocated to Albemarle County through the SSYP include state and federal funds for a variety of road improvement programs. The SSYP for Albemarle County is updated and approved annually and identifies the specific funding source, use, and levels allocated for the immediate fiscal year. The SSYP also identifies projected funding allocations for the next five fiscal years. The Albemarle County Priority List for Secondary Road Improvements, Unpaved Roads is a listing of all Secondary Roads that either the public, a county department, or the Board of Supervisors have requested be paved. This list is reviewed and approved by the Board annually and forms the basis of the SSYP for Albemarle County.

STRATEGIC PLAN: Infrastructure Investment - Prioritize, plan, and invest in critical infrastructure that responds to past and future changes and improves the capacity to serve community needs.

DISCUSSION: The Secondary Six-Year Plan Report April 2023 (Attachment A) provides more detailed background on the SSYP. This report is used to inform the development of the SSYP Draft. The Draft Secondary Six-Year Plan (Attachment A.1) from VDOT provides price projections and fund allocations for projects in t...