Albemarle Logo
File #: 24-405    Version: 1 Name:
Type: Report Status: Presentations
File created: 9/3/2024 In control: Board of Supervisors
On agenda: 10/2/2024 Final action:
Title: Ivy Road Corridor Pipeline Project
Attachments: 1. Att.A - Recommended Ivy Road Corridor Improvements, 2. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA DATE: 10/2/2024

TITLE:
Title
Ivy Road Corridor Pipeline Project
BODY

SUBJECT/PROPOSAL/REQUEST: Requesting Feedback on Proposed Improvement Package

ITEM TYPE: Regular Information Item

STAFF CONTACT(S): Richardson, Wall, Herrick, Filardo, Barnes, McDermott, Swartzendruber, Hersh-Ballering

PRESENTER (S): Hersh-Ballering

LEGAL REVIEW: Yes

REVIEWED BY: Jeffrey B. Richardson

BACKGROUND: VDOT's Project Pipeline program is designed to develop a steady stream - or pipeline - of high-priority projects that address needs identified in Virginia's Transportation Plan (VTrans) and that may be considered for implementation through funding programs such as Smart Scale, Revenue Sharing, and local and regional funding sources. The objective of the Project Pipeline program is to conduct studies across the Commonwealth with a focus on the priority locations and corridors that were adopted during the VTrans process.

The US 29 - US 250/Ivy Road and Old Ivy Road Study is a Project Pipeline study currently in progress within Albemarle County. The study area includes Ivy Road from Ednam Drive to Alderman Road, the US 29 - US 250 interchange, and Old Ivy Road. The study has focused on improving roadway safety, reducing traffic congestion, improving access, and enhancing multimodal accessibility/connectivity. The study process provided multiple opportunities for public input - including two online surveys, public meetings, and a corridor focus group.

STRATEGIC PLAN: Infrastructure & Placemaking - Invest in infrastructure and amenities that create connection, opportunity, and well-being

DISCUSSION: County staff will present the recommended package of improvements for the Ivy Road Corridor to the Board of Supervisors for feedback. The improvements included in this package were identified by the study and are expected to work synergistically to achieve the study's goals of improving safety, reducing congestion, improving access, and enhancing multimodal acces...