AGENDA DATE: 2/18/2026

TITLE:
Three Notched Trail Master Plan Project Update

SUBJECT/PROPOSAL/REQUEST: Presentation on the ongoing Three Notched Trail Shared-Use Path Master Plan

ITEM TYPE: Regular Information Item

STAFF CONTACT(S): Richardson, Wall, Herrick, Svoboda, Barnes, McDermott

PRESENTER (S): Kevin McDermott

LEGAL REVIEW: Not Required

REVIEWED BY: Jeffrey B. Richardson

BACKGROUND: Albemarle County was awarded just over $2,000,000 in Rebuilding American Infrastructure with Sustainability and Equity (RAISE) grant funds to develop a Master Plan for a future Three Notched Trail Shared Use Path connecting Charlottesville to the Blue Ridge Tunnel at Afton. The trail is intended for use by walkers, joggers, cyclists, and other non-motorized users, and is anticipated to provide broad-ranging community benefits including health benefits, tourism growth, and economic development. Similar trails, such as the Virginia Capital Trail, have delivered these types of benefits on a local, regional, and statewide scale. The scope of the Master Plan includes four major planning tasks:

- Evaluate route options and conduct an alternatives analysis of up to three potential path alignments
- Conduct stakeholder and public engagement to determine a preferred alignment;
- Reach functional (30%) design for priority sections of the preferred alignment; and
- Develop an implementation plan for the shared use path that identifies segments of the alignment that would have independent utility if constructed separately.

This is a planning grant only and additional funding must be sought for project construction. Staff finalized the grant agreement with FHWA and released an RFP for consultants in early April 2024. Vanasse Hangen Brustlin, Inc. (VHB) along with sub-consultants Toole Design and EPR, were chosen and a Notice to Proceed was issued in February 2025.

STRATEGIC PLAN: Infrastructure & Placemaking - Invest in infrastructure and ame...