Albemarle Logo
File #: 24-405    Version: 1 Name:
Type: Report Status: Presentations
File created: 9/3/2024 In control: Board of Supervisors
On agenda: 10/2/2024 Final action:
Title: Ivy Road Corridor Pipeline Project
Attachments: 1. Att.A - Recommended Ivy Road Corridor Improvements, 2. Presentation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA DATE:  10/2/2024

 

TITLE:

Title

Ivy Road Corridor Pipeline Project

BODY

 

SUBJECT/PROPOSAL/REQUEST:   Requesting Feedback on Proposed Improvement Package

 

ITEM TYPE:  Regular Information Item

 

STAFF CONTACT(S):  Richardson, Wall, Herrick, Filardo, Barnes, McDermott, Swartzendruber, Hersh-Ballering

 

PRESENTER (S):  Hersh-Ballering

 

LEGAL REVIEW:   Yes

 

REVIEWED BY: Jeffrey B. Richardson

 

BACKGROUND:  VDOT’s Project Pipeline program is designed to develop a steady stream - or pipeline - of high-priority projects that address needs identified in Virginia’s Transportation Plan (VTrans) and that may be considered for implementation through funding programs such as Smart Scale, Revenue Sharing, and local and regional funding sources. The objective of the Project Pipeline program is to conduct studies across the Commonwealth with a focus on the priority locations and corridors that were adopted during the VTrans process.

The US 29 - US 250/Ivy Road and Old Ivy Road Study is a Project Pipeline study currently in progress within Albemarle County. The study area includes Ivy Road from Ednam Drive to Alderman Road, the US 29 - US 250 interchange, and Old Ivy Road. The study has focused on improving roadway safety, reducing traffic congestion, improving access, and enhancing multimodal accessibility/connectivity. The study process provided multiple opportunities for public input - including two online surveys, public meetings, and a corridor focus group. 
 

 

STRATEGIC PLAN: Infrastructure & Placemaking - Invest in infrastructure and amenities that create connection, opportunity, and well-being

 

DISCUSSION:  County staff will present the recommended package of improvements for the Ivy Road Corridor to the Board of Supervisors for feedback. The improvements included in this package were identified by the study and are expected to work synergistically to achieve the study’s goals of improving safety, reducing congestion, improving access, and enhancing multimodal accessibility/connectivity. Also, the public rated this package of improvements most favorably (as compared to other proposed improvement packages) in the online survey.

 

BUDGET IMPACT: There is no budget impact at this time. Pipeline Program studies, including the Ivy Road Corridor study, are fully funded by VDOT. The package of improvements (or a subset) may be funded using either Smart Scale - which does not require any local match for project applications - or Revenue Sharing - which requires a 50% local match. If/when County staff is ready to recommend submission of application(s) for Ivy Road Corridor improvements to either of these programs, staff would return to the Board for resolution(s) of support at that time.  

 

RECOMMENDATION:

Recommendation

Staff recommends that the Board share feedback on the potential improvements presented and their relative priority.

 

ATTACHMENTS: 
A - Recommended Ivy Road Corridor Improvements