File #: 22-293    Version: 1 Name:
Type: Resolution Status: Consent Agenda
File created: 4/27/2022 In control: Board of Supervisors
On agenda: 5/18/2022 Final action:
Title: Scottsville Downtown Pedestrian Improvement Project Support
Attachments: 1. A - Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

AGENDA DATE:  5/18/2022

 

TITLE:

Title

Scottsville Downtown Pedestrian Improvement Project Support

BODY

 

SUBJECT/PROPOSAL/REQUEST:   Request to approve contributing $60,000 to the Town of Scottsville for its Downtown Pedestrian Improvement Project

 

ITEM TYPE:  Regular Action Item

 

STAFF CONTACT(S):  Richardson, Hudson, Bessette, Birch, Sumner, Lin

 

PRESENTER (S):  N/A

 

LEGAL REVIEW:   Yes

 

REVIEWED BY: Jeffrey B. Richardson

 

BACKGROUND:  The Town of Scottsville is undertaking a downtown pedestrian improvement project.  The total project cost is $400,000, with $320,000 provided through the Transportation Alternatives Program of the State’s Commonwealth Transportation Board. The Town has pledged $80,000 of local funding to support the project. The anticipated project completion is December 2024. 

 

STRATEGIC PLAN: Mission - To enhance the well-being and quality of life for all community members through the provision of the highest level of public service consistent with the prudent use of public funds.

 

DISCUSSION:  The Scottsville downtown pedestrian improvement project will construct sidewalks along Bird Street, Harrison Street, and Main Street, including sidewalk access to the Scottsville Library, a branch of the Jefferson-Madison Regional Library. Crosswalks and curb ramps will be installed, providing safety and ADA access.   

Supporting the Town with a $60,000 contribution for the VDOT-approved downtown pedestrian improvement project would provide a much-needed public amenity to the southern portion of the County, as well as offset a portion of the Town’s required local project contribution.

 

BUDGET IMPACT: Funding for the $60,000 Scottsville downtown pedestrian improvement project would be supported by General Fund fund balance to be paid to the Town.

 

RECOMMENDATION:

Recommendation

Staff recommends that the Board adopt the attached resolution (Attachment A) to approve the $60,000 contribution.

 

ATTACHMENTS: 
A - Resolution to contribute funding to the Town of Scottsville downtown pedestrian improvement project.